Development lessons for building a 0-1 product at big companies

Earlier in my Facebook career, I built a standalone app. Where many projects at big companies involve incremental changes or modifications to existing surfaces, we had the opportunity to build something from the ground up. Through our successes and tribulations, we learned four key lessons to share with teams building a 0 to 1 product:

  1. Maximize input from research and other functions

  2. Embrace iteration, but avoid last minute thrash

  3. Increase accuracy of the engineering timeline by incorporating variance

1. Maximize input from research and other “Understand” functions

One of the great assets of a large companies that often differentiate them from scrappier startups is the depth of experts. In shaping our app's strategy, we maximized diverse perspectives. Strategies are best when developed in active consultation with people in “Understand” functions whose job it is to synthesize data.

Research and marketing teams often work day in and day out with our target users, so are in consistent conversation to understand needs. Ops teams are on the receiving end of passionate feedback from users, so can share pain points back to the product teams.

Research defined the app's purpose, core functionality, and helped improve our UX. Nearly all our product decisions had roots in a specific insight.

2. Embrace iteration, but avoid last minute thrash

There is a healthy push-pull relationship between embracing iterative work and minimizing thrash.

Facebook has a saying: “We're 1% finished.” Sometimes that's an overstatement! Since we were building something new, we made opinionated product decisions that were sometimes wrong. The team kept adaptive as our product and designs evolved.

Product feedback came at various stages of the process, and sometimes it took having an actual build we could dogfood to understand a feature's implications. It's always easier to move a button in a design file than it is to rewrite code, but reverting a feature doesn't need to be “churn;” it's the iterative process at work.

On the other hand, eleventh hour changes are painful. With less time to address changes, late-breaking feedback forces compromises to work-life balance, code quality, or even the product itself. To reduce the likelihood of disruptive feedback, consider these lessons:

  1. Set clear expectations with leadership: We did not galvanize the scrutiny we needed with our product leadership early enough. We thoroughly reviewed product goals and strategy, but did not provide sufficient visibility into what we were building (and when we did, it was too much an after thought). To remedy this, we should have established a “one way door”: solicit prescriptive product feedback when there's sufficient time to pivot, rather than late (once code complete or “through the door”), when it'll ignite a firedrill. Another trick is to find a forcing function. Use milestones like public tests and betas or senior exec reviews to spawn the internal attention that a big launch otherwise precipitates.

  2. Budget time for dogfooding and soak: If I could speak with my past self, I'd say, Finish roadmapping. Identify a launch date. Now push it back by.” Budgeting time for quality polish is critical. All the theorizing in the world can't replace the experience of testing the real thing. The challenge is to use dogfooding and soak time earnestly, rather than as an opportunity to accelerate last minute feature development that could on its own create new regressions and bugs.

3. Increase accuracy of engineering timeline by incorporating variance

We committed externally to shipping the app before a specific date. As we conceptualized the app, we estimated build times so we knew how much we could fit in our MVP. Unfortunately, our timelines kept slipping. We identified several ways to increase accuracy of forecasts:

  1. Be honest, and remove implicit pressures: Internal or external pressures beget unrealistic timelines. There may be a date we want to hit, but setting false expectations is counter-productive. Engineers or designers should be the ones generating estimates, and ought to prioritize honesty. For project managers likes PMs, EMs, and designer managers, remove implicit pressures and frame questions that solicit genuine responses (“What is a realistic range for how long this will take?” vs. “Do you think you can get this done by Friday?”).

  2. Create estimates as a range: High variance in build times is inevitable as unexpected obstacles arise...or don't. Engineers can consider providing an estimate as a range (“My best guess is 1 week. Best case I'll be done in 5 days, worst case it'll take 2 weeks.”) rather than as an absolute (“1 week”). As important, communicate risks early and often so we can narrow and shift timelines accordingly.

  3. Vocalize risks and tradeoffs: As execs are keen to say, everything is a prioritization problem. The whole team has responsibility to identify tradeoffs. Could we get this done faster if we simplified a feature in a certain way? Is a bigger upfront investment worthwhile to reduce tech debt down the road? The more internally communicative we are, the more we can evaluate tradeoffs with intention.